JH UPDATE
According to Mr Ramsey, the roof is coming along nicely on west addition.
JH UPDATE
Mrs Morrison’s new window is squeaky clean, the locker room floor looks amazing, and the secretary’s furniture just arrived!!
Updated: Open House Schedule - http://5il.co/47ih
JH UPDATE
Here are some pics of Day 3 with no power, ugh.....we just keep saying it will be so AWESOME when completed!
Hillsboro Faculty and Staff Retirees!! You are cordially invited to the Hillsboro R3 Retired Staff Homecoming Brunch - September 22 - Please click link for more info and to download the RSVP form - http://5il.co/47nf
JH UPDATE
Roof going on west addition, temporary doors built for student safety, and wiring in computer class being installed.
Thanks to all of our helpers today who made our JH Trails much better for our community to use. We cleared 1/2 of them and they look great!
ATTN: runners/volunteers:
The JH needs help completing trails. We are working Tues, 7/31, from 7-10am. Shovel/rake/water/spray or just you!
JH School Supply Lists
www.hsdr3.org OR App
Schools>Junior High>Menu>Documents
We have a list for each grade level.
Tax Free Aug 3rd-5th.
JH Schedules will be available on Parent Portal/Infinite Campus on Thursday, August 2. We want you to have access before Tax Free Weekend!
JH OPEN BUILDING NIGHTS
Aug 13 & 14
4-7 pm
Informal, drop off supplies, walk schedule, practice lockers, ask questions.
Limited parking!
No Open House or 7th Verification Days due to construction.
INSTEAD, we will have 2 OPEN BUILDING NIGHTS on Mon 13th and Tue 14th, 4-7pm
JH UPDATE
Boys locker rooms being painted and gym windows are awesome! A/C unit being delivered next week for the gym.
JH Sports begin on Mon, Aug 13 at 3:00. CC and VB will be at JH, FB at the field house. You MUST have current physical, inc. insurance info!
For all the latest, follow Hillsboro R-III Schools on Twitter! @Hillsboro_R3
JH UPDATE
Steel going up and science rooms have paint. They are also leveling the science floors!!!
JH UPDATE
Steel is here for the west addition deck.....we have been waiting for this so the gas line can be reconnected!
JH UPDATE
Faculty RR are a work in progress but will be ADA compliant when finished.
JH UPDATE
Lots of new exterior doors, windows for gym and offices, and brick for west addition. SCHOOL WILL START ON TIME!
For your fridge - 2018-2019 School Calendar - http://5il.co/43ac 😊 First Day of School is Thursday, August 16th!