Lots of plumbing for science lab stations, they need water and gas lines.
And we have WALLS going up for the west addition!
Working, and relaxing, on our new JH Trails. Excited to have students, athletes, faculty, community use them. So peaceful on back 30 acres!
JH UPDATE
Pouring concrete for classes! And this small speaker doesn’t seem big, but new intercom system will add clarity and security.
HJH TRAILS: Culvert 1/3 installed today.
Anyone have a connection for gravel delivery? Would like to put down 10 loads of fine gravel.
JH UPDATE
Close to pouring concrete floor on West addition. Drywall in offices have mud/tape. Art supply room has nice big door.
JH UPDATE
Offices have drywall, safer entryway being framed out, rain is delaying outdoor work but getting a lot done inside.
JH UPDATE
Boys locker room walls are almost up, bleachers installed, and gym AC ductwork being lifted. (Gym was probably 110* today!)
Public Informational Meeting - July 11 @ 6:00 p.m. at the Learning Center - This meeting will include presentations from two search firms discussing their processes in conducting the search for superintendent candidates for the 2019/2020 school year for the Hillsboro R3 School District.
JH UPDATE
Boys locker room doors installed, east wing footings poured, offices are framed out and HJH bleachers are 90% completed.
JH UPDATE
Monday morning at 9am and a lot going on!
Framing offices
New HVAC in gym
New Bleachers in gym
More progress on the JH Trails today, probabably 75% cut out.
We have some pretty big hills, camera pic doesn’t do it justice!
Starting to look like a trail!
It will be a great place behind JH to run/walk/see nature. Hope to be 1-1/2 miles long, more info to come!
JH UPDATE
This may not seem like a BIG deal, but it is my fav part of project! This is where our new, and safer, entry will be installed!
JH UPDATE
HVAC ducts showed up today, we will finally have AC in the Steighorst Gym! Also, office wall framing begins Monday.
JH UPDATE
East wing is compacting gravel base while west wing is close to pouring foundation. Interior office doors are being set.
JH UPDATE
It seems Mr & Mrs Holland’s rooms are getting messy before they get better.
JH UPDATE
Brockmiller treching lines by Annex while I spread dirt on softball field and by BB courts using Bobcat....didn’t get it stuck!
JH UPDATE
If you like digging trenches with big equipment or shovels, the JH is your place to be!
Footings in front & water lines in back.